Video report from the MECENAT construction site on November 28, 2025

The formwork of the floor slab above the underground level of the future parking lot has been completed in section 4.

The foundation slab of section 3 has been concreted, and reinforcement and concreting of the vertical elements of the underground level of the parking lot are currently underway.

The foundation slab of sections 5-6 has also been concreted.

The installation of sheet piling for the excavation pit from bored injection piles and corresponding grillages along sections 1-2 and the office building has been completed.

Excavation work for the excavation pit of sections 1-2 and the office tower is in progress.

A tower crane has been installed to provide work on sections 3-5. The foundation for the second tower crane has been concreted, which will provide work on the 6th residential section and the office tower.

The asphalt concrete coating of the intra-block driveway from Knyahyni Olhy St. has been restored.