Video report from the MECENAT construction site as of August 19, 2026

Video report

Monthly Construction Progress Highlights:

Sections 3–4:

  • Masonry work has reached the top (8th) floor. Technical roof structures are being constructed in parallel.
  • Installation of Reynaers Aluminium window systems is ongoing at the 4th–5th floor level.
  • Double-glazed window units are being installed in apartments on the 2nd–3rd floors, with units lifted to the 4th–5th floors for upcoming installation.
  • Installation of the storm sewer system has commenced.

Sections 5–6:

  • Preparations for external masonry and internal partition walls are underway; ceramic blocks are being delivered to the upper floors.
  • Foundation pit backfilling is in progress.

Sections 1–2:

  • Monolithic work for the vertical elements of the 5th floor is nearing completion; formwork for the slab above is currently being installed.

Section 7:

  • Formwork setup for concreting the slab above level -2 of the underground parking is in its final stages.

Stylobate Area:
Excavation of the pit for the stylobate structure is ongoing. This space will unite all sections and house part of the two-level underground parking.

The green roof above will feature a landscaped courtyard with greenery, modern amenities, and dedicated leisure areas for residents.