A new important stage has begun - the masonry of external and inter-apartment walls in sections 3 and 4:
- Section 4
In a month, the reinforced concrete frame was raised by two more floors. The installation of vertical elements of the 7th ground floor is in progress. The masonry of external and inter-apartment walls with ceramic blocks is in progress on floors -1, 1, 2.
- Section 3
The installation of the floor slab over the 6th residential floor is in progress. In parallel, the masonry of the walls of floors -1, 1 and 2 also started.
- Sections 5–6
The floor slab over the 3rd residential floor has been concreted.
- Sections 1–2
Active work in the underground part: reinforcement of the floor above the -2 parking level is in progress.