Video report from the MECENAT construction site as of May 10, 2026

A new important stage has begun - the masonry of external and inter-apartment walls in sections 3 and 4:

  • Section 4

In a month, the reinforced concrete frame was raised by two more floors. The installation of vertical elements of the 7th ground floor is in progress. The masonry of external and inter-apartment walls with ceramic blocks is in progress on floors -1, 1, 2.

  • Section 3

The installation of the floor slab over the 6th residential floor is in progress. In parallel, the masonry of the walls of floors -1, 1 and 2 also started.

  • Sections 5–6

The floor slab over the 3rd residential floor has been concreted.

  • Sections 1–2

Active work in the underground part: reinforcement of the floor above the -2 parking level is in progress.