Video report from the MECENAT construction site on October 08, 2025

The high-voltage power cable of the power grid has been moved outside the construction site to continue the development of the excavation along sections 1-2.

The removal of the sewer network outside the construction site is being completed for further work on the construction of the excavation under the 6th residential section and the office tower.

Concrete preparation (concrete base) has been completed for the foundation slab of sections 3, 4 and 5.

Work on reinforcing the foundation slab of sections 3-4 is ongoing.

In addition to the construction, we are also laying the “foundation” of good neighborly relations – a section of the sewer network has been replaced and landscaping has been restored at the site of the work in the parking lot of the neighboring Business Center.