The removal of the existing heating network outside the construction site has been completed.
For safe pedestrian traffic, a construction gallery has been arranged along Knyahyni Olhy St.
The installation of sheet piling for the excavation from bored injection piles along 4, 5, 6 residential sections and the office tower has been completed. A monolithic beam connecting the piles has also been concreted for further excavation.
The installation of sheet piling for the excavation from solid foundation blocks along 2, 3 and 4 sections has been completed.
The construction of the excavation under the 4th section has been completed. Excavation work is underway to construct the excavation for the future 3rd section.
Measures have been taken to temporarily lower the groundwater level for further construction of concrete preparation under 3, 4 and 5 sections.
They are completing the concrete preparation (under-concrete) for the foundation slab of section 4 (at the corner of Naukovaya and Knyahyni Olhy streets) and are starting on section 3. We are preparing to reinforce the foundation slab of section 4.
We have delivered road slabs for arranging a passage along Knyahyni Olhy street.
We have prepared a site (foundation) for concreting the foundation for the first tower crane.
Video report from the MECENAT construction site on September 04, 2025