Video report from the MECENAT construction site as of April 2, 2026

The project is steadily gaining momentum − work is being carried out simultaneously in several sections:

  • Section 4

Over the past month, the 2nd and 3rd floors have been completely erected. Formwork is currently being installed for the installation of the floor slab above the 4th ground floor.

  • Section 3

Concreting of the floor slab above the 3rd floor is underway.

  • Sections 5–6

The installation of two levels of underground parking and vertical structures of the 1st floor has been completed. Preparations are underway to form the floor slab above the commercial block.

  • Sections 1–2

Concreting of the foundation slab has been completed - a reliable foundation has been formed for further floor additions.

  • Non-residential building

The foundation slab has also been installed.