Video report from the MAVERICK construction site, May 2026

Video report


Phase I

Building 23B

  • Commissioned. Final stage of facade works.

Building 23V

Section 1

  • Clinker cladding of the upper floors is being completed.

Section 2

  • Clinker facade decoration is being completed.
  • Installation of water supply risers is completed, drainage – at the level of the 8th floor.
  • Installation of doors to the apartments is completed.
  • Lightning protection system installed.

Landscaping:

  • Work on landscaping the yard and adjacent territory is ongoing.

 

Phase II

Section 3:

  • Underground floor – completed. Vertical structures of the 1st floor are in progress.
  • Stylobate gap between sections 2 and 3 – vertical structures of the underground floor (parking) and installation of the floor slab above the parking lot are in progress.

Section 2:

  • The installation of foundations and vertical structures of the underground floor (parking) of the section is in progress.
  • The stylobate gap between sections 1 and 2 is also under foundation work.