Video report from the MAVERICK construction site, June 2026

Video report


Phase 1
We are completing the facade work in section 2 of building 23B. We are waiting for favorable weather conditions to begin landscaping the lawns.

Phase 2

Section 3:

  • The floor slab above the 1st floor has been concreted – 169.5 m3 of concrete has been received and poured in a continuous mode. This space will soon become part of the trade and service infrastructure within the complex.
  • The stylobate gap between sections 2 and 3 – the construction of the reinforced concrete frame of the ground floor.

Section 2:

  • The parking lot's enclosing walls are being erected along the outer perimeter.
  • The base (concrete base) is being made for the arrangement of the floor of the -1st floor.
  • The elevator diaphragm has been installed.
  • The backfilling of the pit sinuses is being carried out.
  • Stylobate gap between sections 1 and 2 – installation of foundations and vertical structures of the underground floor (parking) of the section.

Section 1:

  • Foundation work in progress.