Video report from the MAVERICK construction site, July 2026

Video report

We share the achievements and progress of the work in July.

Section 3:

  • We are actively growing upwards — forming the formwork for concreting the floor slab above the 3rd floor.
  • In parallel, we have begun laying the external and internal walls of the 1st floor.

Stylobate between sections 3 and 2:

  • The construction of the vertical structures of the 1st floor is ongoing.

Section 2:

  • Monolithic works are ongoing — the floor slab above the 1st floor has been arranged.

Stylobate between sections 2 and 1:

  • Vertical structures of the underground level (parking lot) are in operation

Section 1:

Foundation works are ongoing.