Video report
We share the achievements and progress of the work in July.
Section 3:
- We are actively growing upwards — forming the formwork for concreting the floor slab above the 3rd floor.
- In parallel, we have begun laying the external and internal walls of the 1st floor.
Stylobate between sections 3 and 2:
- The construction of the vertical structures of the 1st floor is ongoing.
Section 2:
- Monolithic works are ongoing — the floor slab above the 1st floor has been arranged.
Stylobate between sections 2 and 1:
- Vertical structures of the underground level (parking lot) are in operation
Section 1:
Foundation works are ongoing.