Building 23V
Section 1
- The facade of the upper floors is being finished with clinker.
Section 2
- Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
- The heating and water supply pipes are being laid. The installation of the heating system risers is in progress.
- The installation of the electrical panel equipment is being completed.
- The walls of the common areas are being decorated with decorative plaster.
Building 23B
Section 1
- Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
- The installation of heating points in the apartments has begun.
Section 2
- Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
- The installation of the water supply system risers is in progress.
- The installation of the household sewage risers has been completed.
- Installation of fire protection system signs and alarms is underway.
- Finishing work in common areas is complete.
Lobby:
- Installation of decorative elements of the suspended ceiling and painting of the walls are being completed.
Parking:
- Installation of sectional gates of the entrance group.
- Installation of plumbing equipment in the shelter.
Landscaping:
- The construction fence has been moved. Laying of paving slabs on the side of the house along Slavyanskaya Naberezhna has been completed. The passage has been opened for pedestrians.
- Work continues on landscaping the yard and the side of the house from the Budapest Residential Complex.
External networks:
- Work is being completed on connecting the complex to the city gas supply system.
- The water supply and sewage systems have been connected to the city networks, certificates confirming compliance with technical specifications have been received.