Video report from the MAVERICK construction site as of February 9, 2026

Building 23V

Section 1

  • The facade of the upper floors is being finished with clinker.

Section 2

  • Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
  • The heating and water supply pipes are being laid. The installation of the heating system risers is in progress.
  • The installation of the electrical panel equipment is being completed.
  • The walls of the common areas are being decorated with decorative plaster.


Building 23B

Section 1

Section 2

  • Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
  • The installation of the water supply system risers is in progress.
  • The installation of the household sewage risers has been completed.
  • Installation of fire protection system signs and alarms is underway.
  • Finishing work in common areas is complete.


Lobby:

  • Installation of decorative elements of the suspended ceiling and painting of the walls are being completed.

 

Parking:

  • Installation of sectional gates of the entrance group.
  • Installation of plumbing equipment in the shelter.

 

Landscaping:

  • The construction fence has been moved. Laying of paving slabs on the side of the house along Slavyanskaya Naberezhna has been completed. The passage has been opened for pedestrians.
  • Work continues on landscaping the yard and the side of the house from the Budapest Residential Complex.

 

External networks:

  • Work is being completed on connecting the complex to the city gas supply system.
  • The water supply and sewage systems have been connected to the city networks, certificates confirming compliance with technical specifications have been received.