Video report from the MAVERICK construction site as of March 6, 2026

Building 23V

Section 1

  • The facade of the upper floors is being finished with clinker.

Section 2

  • The installation of metal structures of the ventilated facade, insulation and clinker finish is in progress.
  • The installation of the heating system risers is being carried out.
  • The installation of the electrical panel equipment is being completed.
  • The decoration of the walls of public areas with decorative plaster is in progress.


Building 23B

Section 1

  • The facade of the upper floors is being finished with clinker.
  • The installation of heating points in the apartments has been completed, underfloor convectors are being installed on floors 3-10.
  • Electricity meters have been installed.

Section 2

  • The decoration with clinker is in progress.
  • The water supply system risers have been installed.
  • The installation and connection of the domestic sewage system of the section in the parking lot is in progress.
  • The installation and disconnection of the electrical panel equipment has been completed.
  • Electricity meters have been installed.
  • On the 8th-9th floors, apartment doors are being installed.


Lobby:

  • Installation of decorative elements of the suspended ceiling and painting of the walls have been completed.

Parking:

  • Drainage pumps have been installed.
  • Installation of plumbing equipment in the shelter has been completed.

Landscaping:

  • Work continues on landscaping the yard and the adjacent area from the Budapest Residential Complex.