Building 23V
Section 1
- The facade of the upper floors is being finished with clinker.
Section 2
- The installation of metal structures of the ventilated facade, insulation and clinker finish is in progress.
- The installation of the heating system risers is being carried out.
- The installation of the electrical panel equipment is being completed.
- The decoration of the walls of public areas with decorative plaster is in progress.
Building 23B
Section 1
- The facade of the upper floors is being finished with clinker.
- The installation of heating points in the apartments has been completed, underfloor convectors are being installed on floors 3-10.
- Electricity meters have been installed.
Section 2
- The decoration with clinker is in progress.
- The water supply system risers have been installed.
- The installation and connection of the domestic sewage system of the section in the parking lot is in progress.
- The installation and disconnection of the electrical panel equipment has been completed.
- Electricity meters have been installed.
- On the 8th-9th floors, apartment doors are being installed.
Lobby:
- Installation of decorative elements of the suspended ceiling and painting of the walls have been completed.
Parking:
- Drainage pumps have been installed.
- Installation of plumbing equipment in the shelter has been completed.
Landscaping:
- Work continues on landscaping the yard and the adjacent area from the Budapest Residential Complex.