Video report from the MAVERICK construction site on June 30, 2025

Building 23V
Section 1

  • Installation of Buderus gas condensing boilers and equipment is complete.
  • Finishing of the facade with clinker is in progress.
  • The distribution of engineering networks to the apartments and heating in the apartments is completed. In the commercial premises of the 1st floor, the distribution of heating is being completed.
  • Arrangement of screed – in the apartments is completed, in progress in the commercial premises of the 1st floor.
  • Handrails are installed on the interfloor stairs.
  • Low-voltage networks on the residential floors are completed.
  • Elevator cabins are installed, commissioning work is in progress.

Section 2

  • Masonry of the walls of the 8th floor, roof boiler room and arrangement of ventilation ducts.
  • Installation of window structures made of warm aluminum profile from Schuco and glazing with two-chamber multifunctional double-glazed windows – 4-5 floors.
  • Plastering of walls of public areas – 2-3 floors.
  • Fire safety cable lines are being laid.



Building 23B
Section 1

  • Installation of metal structures of the ventilated facade, insulation and clinker finishing is underway.
  • Boilers are installed in the boiler room, equipment is being installed.
  • Heating and water supply to the apartments is completed. Domestic sewage is ready for floors 3-8.
  • Heating in the apartments is completed, work is being completed in the commercial area.
  • Screed arrangement in the commercial premises of the 1st floor, apartments – completed.
  • Installation of electrical panel equipment is underway.
  • Handrails are installed on the interfloor stairs.
  • Installation of elevator equipment is underway.
  • Decoration of the corridor walls with decorative plaster begins, preparation for decoration of the elevator halls.
  • Low-voltage networks on residential floors – completed.


Section 2

  • Floor screed on the terraces is concreted.
  • Window structures and glazing – work on floors 6-8.
  • The laying of cable lines for electrical networks and fire safety has been completed.


Parking:

  • Work on arranging the floor surface is in progress.

Landscaping:

  • Paving tiles are being laid in the courtyard.
  • On the side street along Slavyanskaya Naberezhna, crushed stone has been compacted for further stages of landscaping.
  • Plastering work in the lobby.

External networks:

  • Gas networks are being laid across the site.
  • The walls of the built-in transformer substation are being built.