Video report from the MAVERICK construction site on December 30, 2025

Building 23V

Section 1

  • The facade of the upper floors is being finished with clinker.
  • Architectural lighting of the facade has been installed.

Section 2

  • Glazing – work has been completed after dismantling the lift.
  • Installation of metal structures of the hinged ventilated facade, insulation and clinker decoration is in progress.
  • The laying of heating and water supply pipes is being completed.
  • The ventilation system has been installed – completed.
  • The fire protection system has been installed – completed.
  • The elevators have been installed, commissioning work is being carried out.
  • The floor screed on the floors is being completed, the laying of porcelain stoneware in common areas is ongoing.
  • The decoration of the walls of common areas with decorative plaster has begun – work on floors 4-5.


Building 23B

Section 1

  • Installation of metal structures of the hinged ventilated facade, insulation and clinker finish is in progress.
  • Architectural lighting of the facade has been installed.

Section 2

  • Installation of metal structures of the ventilated facade, insulation and clinker finish is in progress
  • Installation of the heating system risers – completed.
  • Installation of the household sewage system risers is in progress – work on the 3rd floor level.
  • Porcelain stoneware on the floor in common areas – laid, on the 10th floor, wall decoration with decorative plaster is in progress.

Lobby:

  • Finishing work is in progress.

Parking:

  • Work on the construction of the entry/exit ramp is being completed.

Landscaping:

  • In the courtyard and on the adjacent territory from the side of Radishcheva Street, paving slabs are being laid. Soil has been delivered for the formation of flower beds.

External networks:

  • Work is underway to connect the complex to the city gas supply system.