Video report from the MAVERICK construction site on April 30, 2025

Building 23V
Section 1

  • We are starting the installation of roof elements of smoke exhaust (equipment is already on site).
  • Along the outer perimeter of the section – installation of metal structures of the ventilated facade and non-combustible basalt insulation. From the inner courtyard – on floors 9-10, insulation is being completed.
  • Finishing with clinker – from the side of Radishcheva Street and Slavyanskaya naberezhna.
  • The floor screed on the terraces of the upper floors has been concreted.
  • Distribution to the apartments of heating, water supply, electrical networks and supply and exhaust ventilation – completed.
  • Distribution of heating pipes in the apartments – completed on floors 4-8, 10.
  • Installation of slow-flow networks is in progress.
  • Finishing of common areas: laying of porcelain stoneware on the floor of the inter-apartment corridors has been completed, samples of suspended grilyato ceilings have been installed.
  • Installation of elevator equipment is in progress.

Section 2

  • Monolith – completed.
  • Masonry of external and internal walls – work on 5-6 floors.
  • Installation of window structures based on warm aluminum profiles from Schuco and glazing with two-chamber multifunctional glass units – 2-4 floors.
  • Plastering of walls of common areas – 3-4 floors.

 

Building 23B
Section 1

  • Roofing work in progress.
  • Along the outer perimeter of the section – installation of metal structures of the ventilated facade and non-combustible basalt insulation. From the courtyard – installation of insulation on 9-10 floors.
  • Glazing and niches for air conditioners – completed.
  • Distribution of heating and water supply pipes to the apartments – completed.
  • Electrical installation work in progress.
  • Сommon areas decoration: plastering of walls of – completed, laying of porcelain stoneware on the floor continues.

Section 2

  • Monolith completed.
  • Wall laying – reached the 9th floor level.
  • Window structures based on warm aluminum profiles from Schuco and glazing – works on floors 3-5.

 

Parking:

  • In sections V1 and B1, masonry of the walls of technical premises continues.

 

One of the three tower cranes has been dismantled – the planned scope of work for it has been completed.