Video report from the MAVERICK construction site as of April 30, 2026

Video report

Phase І

Building 23V
Section 1

  • The upper floors of the facade are being finished with clinker cladding.
  • Glass railings of french balconies have been installed.

Section 2

  • Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
  • Installation of water supply and drainage risers is in progress.
  • Installation of doors to apartments has begun.


Building 23B
Section 1

  • The cladding of the ventilated facade and laying of tiles on the terrace floor have been completed.
  • Glass railings of french balconies have been installed.
  • The metering units in the commercial sector have been installed.

Section 2

  • The facade is being finished with clinker decoration.
  • The installation of underfloor convectors continues.
  • The metering units in the commercial sector have been installed - completed.

Lobby:

  • The clinker decoration of the entrance group has been completed.
  • The installation of the decorative suspended ceiling lighting has been completed.

Landscaping:

  • Work is underway on landscaping the yard and the adjacent territory.
  • Play complexes on the playgrounds and equipment on the sports field have been installed.


Phase II

The development of the excavation is underway.

Section 3

  • The foundations and concrete preparation for the future floor under the section have been completed.
  • The vertical elements (walls/columns) of the underground floor (parking) of the section are in progress.
  • The stylobate gap between sections 2 and 3 is under reinforced concrete foundations.

Section 2

The reinforced concrete foundations of the section are in progress.