Video report from the MAVERICK construction site on May 28, 2025

Building 23V
Section 1

  • Roof elements of the smoke exhaust system have been installed.
  • Equipment installation continues in the boiler room and heat point. Buderus Logamax plus gas condensing boilers have been installed.
  • Installation of metal structures of the ventilated facade and non-combustible basalt insulation is being completed. The facade is being finished with clinker.
  • Heating, water supply, electrical networks and supply and exhaust ventilation to the apartments have been completed. Domestic sewage – on the 9th floor.
  • Heating pipes in the apartments have been installed – floors 3-10. Concreting of the screed is in progress.
  • Installation of low-current networks is in progress.
  • Installation of elevator equipment is in progress.


Section 2

  • Monolith – completed.
  • Laying of external and internal walls – work on the 7th floor.
  • Installation of window structures based on warm aluminum profiles from Schuco and glazing with two-chamber multifunctional glass units is in progress – floors 2-5.
  • Plastering of walls of common areas – floors 2-3.
  • Installation of fire safety systems has begun.


Building 23B
Section 1

  • Roofing work is completed. Floor screed on the terraces of the upper floors has been concreted.
  • Installation of metal structures of the ventilated facade and non-combustible basalt insulation is in progress.
  • Heating and water supply wiring to apartments – completed.
  • Heating pipes in apartments – completed floors 5-6/8-10.
  • Electrical wiring and installation of electrical panels are in progress.
  • Finishing of common areas: plastering of walls – completed, laying of porcelain stoneware on the floor is in progress.

 

Section 2

  • Monolith and masonry completed.
  • Window structures and glazing – work on floors 2-6.
  • Electrical networks and fire safety systems have begun.

Parking: work has begun on arranging the floor surface.

Landscaping:

  • Laying of a multilayer roof over the parking lot – the future courtyard - is underway.
  • Paving slabs are already on the site.

External networks:

  • 2 cabinet gas control points have been delivered to the site.
  • Cable for the transformer substation has been purchased.


Indoor convectors for the apartments of the first sections 23V and 23B have already been delivered.


The second of three tower cranes has been dismantled – the planned scope of work for it has been completed.