Video report from the MAVERICK construction site as of April 2, 2026

Phase I

Building 23V
Section 1

  • The upper floors of the facade are being finished with clinker.
  • The lightning protection system has been installed.
  • Electricity meters have also been installed.

Section 2

  • Installation of metal structures of the ventilated facade, insulation and clinker decoration is in progress.
  • The heating system risers have been installed.
  • Electricity meters have been installed.
  • We are completing the decorative decoration of the walls of public areas.


Building 23B
Section 1

  • The upper floors are being finished with clinker decoration.
  • The lightning protection system has been completed.
  • Heating points and underfloor convectors have been installed in the apartments.
  • Tiles are being laid on the terrace floor.
  • Metering units are being formed in commercial premises.

Section 2

  • Facade decoration with clinker is in progress.
  • The lightning protection system has been installed.
  • The installation of heating points in the apartments has been completed, and this week we will begin installing underfloor convectors.
  • The metering units are being assembled in the commercial sector.
  • The doors to the apartments have also been installed.

Landscaping:

  • Work is underway to improve the yard and the surrounding area, in particular on the side of the Budapest residential complex.


Phase II

  • The excavation is underway. 19,300 m3 has been completed - this is about 59% of the total volume.
  • The foundations of section 3 are 80% ready, 250 m3 of the planned 300 m3 have been poured.