Video report from the MAVERICK construction site on August 07, 2025

Building 23V
Section 1

  • The facade is being finished with clinker.
  • The gas supply pipe is being laid along the facade of the building to the boiler room.
  • The internal engineering networks have been completed. The installation of water supply risers is in progress.
  • Doors have been installed in apartments and commercial premises.
  • The decoration of elevator halls is being completed – 10th floor

Section 2

  • The installation of the multi-layer roof covering of the building is in progress.
  • The masonry of the internal walls is completed.
  • Installation of window structures made of warm aluminum profiles from Schuco and glazing with two-chamber multifunctional double-glazed windows – 5-7 floors.
  • Plastering of walls of public areas – 2-3 floors.

 

Building 23B
Section 1

  • Installation of metal structures of a hinged ventilated facade, insulation and clinker finishing is in progress.
  • Installation of Buderus gas condensing boilers and equipment is complete.
  • Heating, water supply and household sewage systems are installed in apartments.
  • Heating and commercial installations are completed.
  • Doors to apartments and commercial premises are installed.
  • Elevator commissioning is completed.

Section 2

  • Laying of multilayer roofing of the building, terraces and parapets is in progress.
  • Window structures and glazing – work on 9-10 floors.
  • Laying of electrical and fire safety cable lines is completed.
  • Rainwater drainage - completed in the high-rise part of the building.
  • Installation of ventilation system risers is in progress.
  • Heating system pipes have begun.
  • Plastering of walls of common areas – completed.


Parking:

  • Floor surface arrangement is in progress.
  • Reflective marking of columns and walls has begun.
  • A video surveillance system is being installed.

Landscaping:
Paving slabs are being laid in the courtyard and along the Slavyanska naberezhna.


External networks:
Installation of cable lines to the transformer substation has begun in the parking lot.


Apartment heating points are already on site.