Video report from the MAVERICK construction site on September 02, 2025

Building 23V
Section 1

  • The facade is being finished with clinker.
  • The gas supply pipe is being laid along the facade of the building to the boiler room.
  • The installation of water supply risers is complete.
  • The elevator halls are being finished with decorative plaster, and the granite cladding of the elevator portals is in progress.
  • The stairs on the commercial floors are being finished.


Section 2

  • The building's multi-layer roof covering is being laid.
  • Installation of window structures made of warm aluminum profiles from Schuco and glazing with two-chamber multifunctional double-glazed windows - work on the 1st, 9th-10th floors.
  • Plastering of walls of public areas – floors 2-5 completed.

 

Building 23B
Section 1

  • Installation of metal structures of the ventilated facade, insulation and clinker finishing is in progress.
  • The installation of engineering networks is completed.
  • Decorative decoration of corridors – 2-5 floors.

Section 2

  • Laying of multilayer roofing of the building, terraces and parapets is in progress.
  • Window structures and glazing – work on 1, 9-10 floors.
  • Laying of cable lines of electrical networks and fire safety is completed.
  • Laying of heating and water supply pipes in common areas – reached the level of the 4th floor.
  • Laying of heating systems in apartments – work on the 4th floor.
  • Concreting of floor screed in apartments and common areas – 2-3 floors.

 

Parking:

  • Installation of DÜKER sewage system under 1-2 sections has been completed.
  • Arrangement of floor surface under 3-4 sections is in progress
  • Application of reflective marking of columns and walls is in progress.

 

Improvement:

  • Paving slabs are being laid in the courtyard and along the Slavyanskaya embankment.
  • Flower beds are being formed in the courtyard, soil has been brought in.