Video report from the MAVERICK construction site on October 02, 2025

Building 23V

Section 1

  • The facade is being finished with clinker.
  • The gas supply pipe is being laid along the facade of the building to the boiler room.
  • Granite cladding of the elevator portals has been completed.
  • The pressure boosting station has been installed.


Section 2

  • The multilayer roof covering of the building is being laid.
  • Installation of window structures made of warm aluminum profiles from Schuco and glazing with two-chamber multifunctional double-glazed windows – work on the 1st, 9th-10th floors.
  • The laying of cable lines of the fire protection system has been completed.
  • Installation of ventilation risers has been completed.
  • Laying of heating and water supply pipes along the corridors on the floors – floors 2, 3 and 5 have been completed.
  • The heating system in the apartments has begun, the 3rd floor is ready.
  • Plastering of walls of common areas – floors 2-7 have been completed.
  • Work is underway to install a video surveillance system and lay Internet cables.

 

Building 23B

Section 1

  • Installation of metal structures of the ventilated facade, insulation and clinker finishing is underway.
  • Decorative decoration of corridors – floors 2-8 completed.
  • Pressure boosting station installed.
  • Granite cladding of elevator portals – floors 2-7.

Section 2

  • Installation of multilayer roofing of the building has been completed. Roofing of smoke exhaust equipment is underway.
  • Installation of equipment in the roof boiler room is underway.
  • Window structures and glazing – work on floors 1, 9-10.
  • Laying of electrical cable lines has been completed, cabinets have been installed on the floors.
  • Laying of heating and water supply pipes in the corridors – floors 1-6, 10 completed.
  • Heating system installation in apartments – floors 2-8 inclusive completed.
  • Floor screed installation in apartments and common areas – floors 2-6 completed.

Parking:

  • Floor surface installation under 3-4 sections is in progress.
  • Reflective marking of columns and walls is in progress.

Landscaping:

  • Paving slabs are being laid in the courtyard and along Slavyanskaya Naberezhna.