I Stage:
- Monolith, masonry, glazing – completed.
- The finishing of the tower with clinker is being completed, and façade work on the stylobate continues.
- Finishing: floor screed for apartments – 21, common areas – 22-23 floors. Finishing of floors of common areas with porcelain tiles – 21, walls of elevator halls – 4-6 floors.
- Doors to apartments – 22.
- The elevators are installed.
- Installation of fire protection systems.
- Water supply – wiring is completed, installation of risers.
- Heating – pipe distribution on floors 24-25, installation of individual heating units – 21, radiators – 16.
- Stormwater and sanitary sewerage are completed.
- Power supply – 24-25.
- Improvement of the stylobate: tiles were laid along the paths.
Stage II:
- The monolith is completed.
- Masonry, glazing and installation of niches for air conditioners in the tower are completed, except for the 18th floor. Glazing of the stylobate continues.
- Installation of the сurtain ventilated facade subsystem and insulation along the tower façade.
- The installation of Mitsubishi elevators has begun.
- Heating pipe routing – 17th floor. Individual heating units - delivered.
- Plastering walls in common areas – 16. Porcelain tiles on the floors of common areas – 3-11 floors.
Tower:
- Monolith – completed.
- Masonry is completed. Glazing – 31 floors.
- Curtain ventilated facade - installation of aluminum composite panels. Finishing with porcelain stoneware.
- Niches for air conditioners – on the 29th floor.
- Floor screed – 24-25 floor.
- Laying porcelain tiles on the walls and floors of common areas – floors 3-16.
Stylobate:
- Finishing with porcelain stoneware floors and walls of common areas and elevator lobbies.
Internal networks:
- Storm drainage: installation completed. Household – 23-29 floors.
- Heating: distribution to apartments was carried out on the 25th floor.
- Water supply: dilution on the 24-25th floors.
- Power supply: cable laying on the 20th floor.
- Installation of fire safety systems.
Landscaping: paving stones have been laid in front of the building.
House 23V
Section 1
- Reinforcement of columns on the 1st floor of the tower continues.
- Concreting of the covering slab above the -1st floor of the parking lot was carried out.
- The frame is being installed and preparations are underway for concreting the basement floor.
Section 2 – excavation development.
House 23B
Section 1
- Concreting of the foundations for the stylobate and underground parking has been completed.
- The formwork is installed and the enclosing walls of the parking lot are concreted.
- We started manufacturing the metal frames of the columns of the 1st floor.
Section 2 – excavation development.