Digest of construction of DAYTONA GROUP projects — November 2024

MARSHALL

Stage I: launched.

Stage II:

  • Completing the clinker finishing of the tower and stylobate.
  • The final coat of paint has been applied to the cold passages, railings have been installed, and porcelain tiles are being laid on the floor.
  • The lobby finishing is being completed.
  • The application of decorative plaster on the floors is almost complete, painting of the ceilings and installation of suspended grillato structures is ongoing – on floors 3-7. Lighting elements are being installed.
  • Installation of distribution boards in apartments, lighting of the 1st level of the parking lot is ongoing.
  • Improvement of the stylobate and inner courtyard, arrangement of exits from the parking lot.

COMMERCIAL PREMISES: finishing of the facade, arrangement of parking pockets is being completed.

 

MAYAK

  • Curtained ventilated facade – finishing with clinker is being completed.
  • Facade monorail system – work is completed.
  • Mirrors are being installed in the elevator lobbies, call buttons are being installed.
  • Suspended grillato ceilings are being installed in the common areas.
  • Apartment doors have been installed.
  • Stylobate: finishing work is being completed in the lobby, navigation and markings are being applied on levels 3-4 of the parking lot.
  • Heating: installation of underfloor convectors. Commissioning in the boiler room.
  • Fire passages and gabions are being completed on the stylobate. Trees have been partially planted. Paving slabs are being laid on the stylobate terraces.

 


MAVERICK

House 23V
Section 1

  • Monolith – technical floor is being completed.
  • External wall laying – floor 9 is complete, internal walls – up to and including floor 8.
  • Installation of window structures on floors 7-8. Glazing – on floors 3-6.
  • Installation of utility sewage systems is ongoing.
  • Installation of the heating system has begun.

Section 2

  • Reinforcement and concreting of vertical elements of the 3rd floor.


Building 23B
Section 1

  • Monolithic – residential floors completed.
  • Masonry of external walls – on the 7th floor, inter-apartment walls – completed on the 6th.
  • Installation of window structures and glazing on floors 3-6.

Section 2

  • The floor slab above the 3rd floor has been concreted.

Inner courtyard: installation of an exploitable roof over the parking lot.

In the parking lot: installation of storm drains, power supply and lighting cables, DÜKER pipes (Germany) have been delivered for the domestic sewerage system.