MARSHALL
⠀
Stage I:
Construction, finishing and landscaping works are complete.
⠀
Stage II:
- Clinker finishing of the tower and stylobate continues.
- Glazing and niches for air conditioners – completed.
- Elevators are installed.
- Porcelain tiles on the floor of common areas – up to the 21st floor. Installation of granite slopes in elevator lobbies and apartment doors is underway.
- Heating: preparation for installation of radiators. Piping of equipment in the boiler room.
- Installation of domestic sewage continues, storm water – completed.
- Water supply: completed.
- Fire safety: smoke removal – will be completed after finishing, fire alarm and sprinkler system – completed.
- Landscaping on the stylobate.
⠀
COMMERCIAL PREMISES: facade cladding and landscaping.
⠀
- Curtained ventilated facade – finishing with aluminum composite panels and clinker is being completed.
- Installation of the facade monorail system is ongoing.
- Glazing is complete, except for the entrance groups on floors -5 and 1.
- 3 KONE elevators have been launched, 2 more are being installed.
- Finishing of common areas is complete, elevator halls – 70%.
- Decorative plastering has been completed in the lobby, the formation of the art object "rock" is being completed.
- Painting of walls and columns on levels -4-2 of the parking lot.
- Installation of doors to apartments and communication cabinets is being completed.
- Heating: apartment heating points have been installed, installation of in-floor convectors has begun.
- Water supply: completed.
- Electricity supply: cable routing – 80%. Installation of switchboards.
- Fire safety systems: work is being completed.
- Landscaping work on the stylobate. Installation of the playground is complete.
⠀
MAVERICK
House 23V
Section 1
- Concreting columns of the top 10th floor.
- Masonry – up to the 9th floor.
- Installation of stained glass structures and glazing of the 1st floor of the commercial area continues.
- Installation of window structures based on a Schuco profile in apartments on the 3rd and 4th floors.
- Routing of storm sewer pipes.
Section 2
- The floor slab above the -1st floor has been concreted.
⠀
House 23B
Section 1
- Monolithic frame – 8th floor.
- Masonry – up to the 5th floor.
- Installation of stained glass structures and glazing of the 1st floor of the commercial area continues.
Section 2
- Elevator shaft and 1st floor columns are being erected.
⠀
Courtyard: construction of an exploitable roof over the parking lot.