⠀Stage I: Construction, finishing and landscaping work completed.
⠀Stage II:
- Clinker finishing of the tower and stylobate continues.
- Elevator commissioning.
- Finishing continues in the lobby.
- Apartment doors have been installed, utility cabinets are being mounted.
- Painting of ceilings and application of decorative plaster has begun in common areas.
- Heating: installation of radiators.
- Water supply and domestic sewerage: work on floors 17-24.
- Power supply: installation of switchboards in apartments.
- Parking: floor sanding, application of special impregnation and marking.
- Fire safety: completed.
- Landscaping is underway on the stylobate.
COMMERCIAL PREMISES: facade cladding, utility installation nearing completion, landscaping of the territory.
⠀
- Curtained ventilated facade – finishing with clinker.
- Facade monorail system – electrical installation work.
- All 5 KONE elevators have been installed.
- In common areas, we are starting to install suspended grilyato ceilings. The finishing of elevator halls is 90% complete.
- Installation of doors in apartments on floors 26-31.
- Stylobate: glazing of the entrance group on level -5 continues, finishing in the lobby, painting of walls and columns in the parking lot is being completed.
- Commissioning of water supply and drainage networks.
- Heating: installation of underfloor convectors.
- Power supply: supply to apartments on floors 14-27.
- Fire safety: commissioning of systems.
- Landscaping work on the stylobate.
⠀
MAVERICK
House 23V
Section 1
- Monolith of residential floors – completed.
- External wall laying – 9th floor completed, internal – 4-7.
- Installation of window structures on floors 3-6, glazing – 3-4.
- Glazing in the commercial area continues.
- Installation of utility and domestic sewage has begun.
Section 2
- Reinforcement and concreting of vertical elements of the 2nd floor.
Building 23B
Section 1
- Monolith – 10th floor.
- External wall laying – up to and including the 7th floor, internal – 4-7.
- Installation of window structures on floors 3-4.
- Glazing in the commercial area continues.
Section 2
- The floor slab above the 2nd floor has been concreted.
Inner courtyard: construction of an exploitable roof over the parking lot.
Installation of storm drains and power and lighting cables in the parking lot.