Digest of construction of DAYTONA GROUP projects — April 2024

MARSHALL

Stage I:

  • Monolith, masonry, glazing – completed.
  • Cladding with clinker – we complete the façade of the tower and continues into the stylob.
  • Finishing: porcelain tiles on the floor of common areas – 22nd floor, painting of ceilings and walls – 19 each. Lobby – installation of drywall, finishing.
  • We are completing the door installation.
  • The installation of internal engineering and fire protection is being completed.
  • External networks: installation in the boiler room is completed, continues in the transformer substation.
  • Landscaping: arrangement of flower beds on the stylobate, local area – laying paving slabs.


Stage II:

  • The monolith is completed. Masonry – 18th floor (the crane was attached).
  • Glazing and niches for air conditioners are completed, except for the 18th floor. Glazing of the stylobate continues.
  • Installation of a suspended ventilated facade subsystem, insulation and finishing of the tower façade with clinker.
  • Installation of the 2nd Mitsubishi elevator.
  • Internal networks: heating pipes – 21st floor, storm sewer – wiring completed.
  • Smoke removal: installation in the stylobate is completed. Fire alarm – 20th floor
  • Plastering of walls in common areas – 20th floor, porcelain tiles on the floor – 16 each.

Commercial premises: masonry is being completed, roofing work continues.


MAYAK

  • The monolith is completed.
  • Glazing – 30th and 32nd floors.
  • Curtain ventilated facade – installation of aluminum composite panels. Clinker finishing.
  • Niches for air conditioners – 29th floor.
  • We are starting to install elevators.
  • Screed – on the 29th floor.
  • Finishing with porcelain stoneware of the common areas of the stylobate, in the tower – 21st floor.
  • Storm sewer: insulation 32-33 floors. Household – 26-29.
  • Heating: wiring – 30 floors, risers – 2-16. Buderus condensing gas boilers have been delivered.
  • Water supply: distribution – 29th floor, risers – 30th.
  • Power supply: cable laying 27th floor.
  • Installation of fire safety systems.
  • External networks: cabinet gas control point – mounted and connected.


MAVERICK

House 23V
Section 1

  • The columns of the 3rd floor have been concreted, and the installation of the floor slab formwork continues.
  • We completed the roof slab above the 1st floor of the commercial building.
  • We started laying the walls.

Section 2

  • Construction of foundations continues.


House 23B

Section 1

  • The floor slab above the 1st floor of the high-rise and the covering above the commercial area were concreted.

Section 2

  • We started building the foundations.

3 tower crane installed.