I stage:
- The monolith, roof and masonry are complete.
- The roof of the stylobate – the amount of work planned for this period has been completed.
- Glazing of the tower is 99%.
- Finishing of the tower with clinker continues, facade work on the stylobate has begun.
- Interior equipment: completed samples of the finishing decoration of the walls and ceilings of common areas; floor screed for apartments – 10 per floor, common areas – 16 per floor; finishing the floor of common areas with ceramic granite – 16-17.
- Installation of apartment and technical doors.
- Elevators: installation of the 2nd (out of three) cabin.
- The smoke removal system is completed, supply and exhaust ventilation – 8-11 floors.
- Water supply – installation of risers.
- Heating – laying of pipes 19-21 floors.
- Domestic sewage – installation of REHAU Raupiano Plus pipes on the 17th floor.
II stage:
- Tower – monolith completed.
- Masonry of external walls – 23rd floor, facade works – 17th.
- Glazing – 22-23 floors.
- Plastering of walls in common areas – 9-10 floors.
- Heating – distribution of pipes on the 4th floor.
MAYAK
Tower:
- We are completing the monolith – 31-32 floors.
- Masonry of walls – 27. Glazing - 26.
- Facade works – on the 26th floor. A sample of decorative decoration is mounted.
- Designs of niches for air conditioners – 25 each, filling with sandwich panels – 21-24.
- Floor screed, 10th floor.
- Rough plaster in common areas – 16. Laying tiles on the floor of the 4th floor.
- Samples of technical and apartment doors have been installed.
Stylobate:
- Facing the facade with clinker.
- In the parking lot, concreting of the floor is being completed, insulation and painting of the walls is in progress.
Internal networks:
- Heating: distribution in apartments of 19-21 floors.
- Water supply to apartments – on the 16th floor.
- Electricity supply: installation of cable channels in high-rise buildings.
- Fire water main – 20th floor.
- Installation of fire safety systems.
- Installation of curbs, cobblestones and paving slabs in the drive zone -4 level.
- Arrangement of the foundations of the 1st section of the building 23B — reinforcement and concreting of base plates for the future columns of the building frame, their waterproofing and backfilling of the foundation sinuses.
- Earthworks - development of a pit for 1 section of the building. 23B and 1 section of the building. 23B, stylobate part and underground parking.