Digest of construction of DAYTONA GROUP projects — August 2024

MARSHALL

Stage I:

  • The paving slabs along the Naberezhna Pobedy and landscaping on the stylobate have been completed.
  • The clinker cladding of the entrance to the parking lot is being completed.
  • Furniture has been installed in the lobby and the complex logo has been illuminated.

Stage II:

  • The clinker finishing of the tower continues, the installation of the external ventilated facade on the stylobate has begun.
  • Glazing and niches for air conditioners are complete.
  • Elevators have been installed.
  • Heating: piping – 23rd floor, installation of risers. Piping of equipment in the boiler room.
  • Installation of domestic and storm sewerage – completed.
  • Water supply: completed
  • Fire safety: smoke removal – will be completed after finishing, fire alarm and sprinkler system - completed.
  • Plastering of walls in common areas – 24th floor, porcelain tiles on the floor – 21st floor.

COMMERCIAL PREMISES: heating pipes are laid out, screed is being poured.


MAYAK

  • Curtained ventilated facade — installation of aluminum composite panels, clinker finishing of upper floors.
  • Installation of guides for the facade monorail system.
  • Glazing is complete, except for entrance groups on floors -5 and 1. Railings of glass railings are being installed on balconies.
  • 3 KONE elevators have been launched, 2 more are being installed.
  • Doors in apartments – floors 3-29.
  • Installation of porcelain tiles on the floor and walls – 31st floor. Lobby – installation of an art object.
  • Heating: apartment heating points are installed. Equipment is being connected in the boiler room and heat supply station.
  • Water supply: distribution – 30th floor, risers – completed.
  • Power supply: laying the working power cable to the apartments.
  • Fire safety systems: work is being completed.
  • On the stylobate, landscaping work, installation of playgrounds and sports grounds.


MAVERICK

House 23V
Section 1

  • Reinforcement of the columns of the last 10th floor.
  • Masonry – up to the 7th floor.
  • Installation of stained glass structures in the commercial area continues, glazing has begun.

Section 2

  • Concreting of columns and the elevator diaphragm of the -1 floor.
  • Partially concreted the parking pavement between sections 1 and 2.

House 23B
Section 1

  • Monolithic frame – 6th floor.
  • Masonry on floors 1-3.
  • Installation of stained glass structures in the commercial area, glazing has begun.

Section 2

  • Enclosing walls and a ceiling above the -1 floor have been erected.
  • The pavement slab is being concreted over the parking lot between the sections.