I stage:
- Monolith and masonry completed.
- The roof of the stylobate – 2/3 of the work has been completed.
- Glazing of the tower – 99%.
- Warming and decoration of the facade with clinker is in progress.
- Cold transitions are insulated, railings are installed on stairwells.
- Interior decoration: the plastering of the walls of common areas has been completed; floor screed of apartments – 10 each, common areas – 13th floor each; decoration of common areas floor with ceramic granite – 11 each.
- Elevators: installation of the 2nd (out of three) cabins is underway.
- Smoke removal and supply-exhaust ventilation systems – on the 19th floor.
- Water supply – apartment-by-apartment distribution is completed.
- Heating – piping on the 17th floor;
- Domestic sewerage – installation of REHAU Raupiano Plus pipelines on residential floors.
- Electricity supply – wiring to charging stations for electric cars, installation of lamps is laid in the parking lot.
II stage::
- The tower – we are completing the technical premises of the roof.
- Masonry of external walls – 22.
- Installation of brackets for the hinged vent facade, insulation and wind barrier – 17.
- Glazing – on the 20th floor.
- Plastering of walls of common areas – 5-6 floors.
- Heating – piping on the 3rd floor.
MAYAK
Tower:
- Monolith – 31 penultimate residential floors.
- Masonry of walls – 27. Glazing – 26.
- Installation of layers (up to finishing) of the hinged vent facade – on the 26th floor, installation of clinker has begun at the corners of the building.
- Designs of niches for air conditioners – 21 each, filling with sandwich panels – 17-19.
- Floor screed on floors 7-9.
- Rough plaster in common areas – 10 each.
- A sample door to the apartment was installed.
Stylobate:
- Facing the facade with clinker.
- Finishing of technical premises, 75% of technical doors have been installed.
- Concreting of the parking lot floor, painting of the walls is being completed on the -4th floor.
- Laying paving stones in front of the building.
Internal networks:
- Heating: distribution by apartments – 18th floor.
- Water supply to apartments – on the 15th floor.
- Electricity supply: installation of equipment in switchboards in the stylobate.
- Fire-fighting water pipe – on the 16th floor.
- Installation of smoke removal, fire ventilation, fire extinguishing and fire alarm systems.
MAVERICK
- 2 tower cranes have been installed, commissioning works are ongoing.
- Concrete preparation (sub-concrete) for part of the foundations of section 1 was performed.
- Construction of the pit continues.