Digest of construction of DAYTONA GROUP projects — January 2024

MARSHALL

I Stage:

  • Monolith, masonry, external glazing – completed.
  • The finishing of the tower with clinker is being completed, and façade work on the stylobate continues.
  • Interior finishing: floor screed for apartments – 15th floor, screed and ceramic granite finishing of common areas – 21st floor.
  • 106 apartment and all technical doors were installed.
  • The elevators are installed.
  • Installation of fire protection systems.
  • Water supply – pipe routing is completed, installation of risers.
  • Heating – pipe distribution on floors 22-23, radiators on floors 14, installation of heating units in apartments continues.
  • Domestic sewerage – 24-25 floors.
  • Electrical supply – completed 16th floor.


II Stage:

  • The monolith is completed.
  • Wall masonry, glazing and installation of niches for air conditioners in the tower are completed, except for the 18th floor. Glazing of the stylobate continues.
  • Installation of a suspended ventilated facade subsystem and insulation along the tower facade.
  • Mitsubishi elevators have been delivered to the site.
  • Heating – pipe distribution 3-11 floors.
  • Plastering walls in common areas – 11-12 floors. Screeds in common areas – 11th floor, in apartments 4-9.

 

 

MAYAK

Tower:

  • Monolith – a covering slab was completed above the 33rd technical floor.
  • Masonry – 30-31 floors. Glazing – 29.
  • Hinged ventilated facade – installation of aluminum composite panels. Finishing with porcelain stoneware.
  • Niches for air conditioners – on the 27th floor.
  • Floor screed – 19-21 floors.
  • Rough plastering of common areas – 22-23 floors. Porcelain tiles in common areas – 3-9 floors.

Stylobate:

  • Finishing of floors and walls of common areas and the elevator hall with porcelain tiles.
  • Parking – installation of sectional entrance gates TM HÖRMANN.

Internal networks:

  • Storm drainage: installation completed on the 26th floor. Household – work on floors 16-21.
  • Heating: distribution for apartments – 24-25 floors.
  • Water supply to apartments is on the 22nd floor. Installation of risers.
  • Power supply: laying cable lines – 10-14 floors.
  • Installation of fire safety systems.

 

MAVERICK

House 23B
Section 1

  • The foundations are complete. The base for the floor of the -1st floor of the parking lot was concreted.
  • A monolithic beam has been completed and the construction of walls on the -1st floor continues.
  • Construction of the elevator shaft in the parking lot continues.

Section 2 – excavation work continues.


House 23B
Section 1

  • Concreting of the foundations for the stylobate and underground parking continues. Completed – 50%.
  • A monolithic beam was made to construct the walls of the parking lot.
  • The completed foundation slab is the basis for the construction of the elevator shaft.

Section 2 – excavation development.