Stage I:
- Monolith, masonry, glazing – completed.
- Cladding with clinker – we complete the facade of the tower, the stylobate continues.
- Common areas: finishing painting of walls – 24th floor, doors to apartments – installed, lobby – installation of mailboxes.
- Marking in the parking lot.
- Engineering and fire protection – completion of works, commissioning.
- Landscaping: arrangement of children's and sports grounds, outbuildings.
⠀
Stage II:
- The monolith and masonry are complete.
- Installation of hinged ventilated facade and decoration of the tower with clinker.
- Glazing and niches for air conditioners – completed.
- Mitsubishi elevators: installation completed.
- Heating: pipe laying on the 22nd-24th floor, installation of equipment in the boiler room.
- Water supply – dilution by 21.
- Storm sewer: tower – completed, works in the stylobate.
- Electricity supply: 3-5 floors.
- Smoke removal – installation in the tower, fire alarm - wiring completed,
- fire extinguishing sprinkler system – installation in the parking lot is being completed.
- Plastering of walls in common areas – 21-24 floors, porcelain stoneware on the floor – 17.
COMMERCIAL PREMISES: installation of window structures.
⠀
- The monolith is complete. The crane is dismantled.
- Glazing – completed parts of the faucet attachment, lasts for 1 floor.
- Hinged ventilated facade – installation of aluminum composite panels, finishing with clinker.
- Niches for air conditioners – 1st floor and faucet area.
- Commissioning of 2 elevators.
- Doors to apartments – 3-21 floors.
- Ceramic granite decoration of common areas – 27th floor and above. Lobby – installation of plasterboard and ceramic granite.
- Heating: installation of apartment heating points. Buderus condensing gas boilers are installed in the boiler room.
- Water supply: distribution – 29th floor, risers – completed.
- Electricity supply: distribution in common areas – completed on the 18th floor.
- Installation of fire safety systems.
- Installation of gabions, formation of flower beds, planting of trees on the roof of the stylobate is ongoing.
⠀
MAVERICK
Building 23V
Section 1
- Installation of formwork for concreting the floor above the 6th floor.
- Masonry is in progress.
- Concreting parapets on the 2nd floor of commerce.
Section 2
- Arrangement of foundations – 80%. Installation of the reinforcing frame of the elevator diaphragm.
⠀
Building 23B
Section 1
- Form the columns of the 5th floor.
- Masonry on 1-2 floors.
Section 2
- Foundations – 85%, concrete preparation for the future parking lots is underway. The elevator diaphragm is concreted.